This is the overall Scottish Delivery Timeline, which goes into far more detail about our plans than the Project Activity table with milestones for the full UK-wide project. It is the responsibility of each home nation how they choose to project manage their part of the project.

Tasks Lead Start End Duration (Days) Complete Working Days
1 Catch-up with project Paul 06 February 2017 02 March 2017 25 100% 19
1.1 Catch-up with project papers Paul 06 February 2017 19 February 2017 14 100% 10
1.2 Organise Gathering Events (Briefings/Panels/Facilitation) Paul 10 February 2017 24 February 2017 15 100% 11
1.3 Twitter, GlobalGoals, Wiki, Meet-ups set-up Paul/Ruchir 13 February 2017 17 February 2017 5 100% 5
1.4 Gathering Events Paul/Ruchir 22 February 2017 23 February 2017 2 100% 2
1.5 UK Sustainable Development Conference Paul/Ruchir 28 February 2017 01 March 2017 2 100% 2
1.6 UK Project Team Meeting Ruchir 02 March 2017 02 March 2017 1 100% 1
2 Project Planning Paul 01 March 2017 27 March 2017 27 100% 19
2.1 Draft Project Plan/Timeline Paul 01 March 2017 13 March 2017 13 100% 9
2.2 Draft to Project Director Paul 13 March 2017 13 March 2017 1 100% 1
2.3 Draft to Project Team (UK) Paul 13 March 2017 13 March 2017 1 100% 1
2.4 Draft to Internal SCVO Team (Comms/TFN/PolicyPA) for review Paul/RS/Comms 14 March 2017 17 March 2017 4 100% 4
2.5 Comments on draft project plan back to Project Coordinator RS/Comms/PT 20 March 2017 20 March 2017 1 100% 1
2.6 Project Meeting - review project plans (Ruchir, TFN, Comms) Paul 23 March 2017 23 March 2017 1 100% 1
2.7 Revise Project Plan and circulate for sign off Paul 23 March 2017 23 March 2017 1 100% 1
2.8 Project Plan signed off (Ruchir) Ruchir 23 March 2017 27 March 2017 5 100% 3
3 Communications/Engagement Plan Paul 06 March 2017 27 March 2017 22 100% 16
3.1 Draft Initial Paper Paul 06 March 2017 07 March 2017 2 100% 2
3.2 Draft to SCVO Comms/TFN Paul 07 March 2017 07 March 2017 1 100% 1
3.3 Meeting with SCVO Comms/TFN Paul 08 March 2017 08 March 2017 1 100% 1
3.4 Revise Plan and circulate with Project Plan Paul 13 March 2017 14 March 2017 2 100% 2
3.5 Comments on draft plan back to project coordinator Ruchir/Comms/PT 20 March 2017 20 March 2017 1 100% 1
3.6 Revise Communications/Engagement Plan and circulate for sign off Paul 19 March 2017 24 March 2017 6 100% 5
3.7 Comms/Engagement Plan signed off (Ruchir) Ruchir 25 March 2017 27 March 2017 3 100% 1
4 Global Goals Website Planning Paul 08 March 2017 23 March 2017 16 100% 12
4.1 Meetings with Ruchir, David Hope Jones and David McNeill Ruchir/Paul 08 March 2017 09 March 2017 2 100% 2
4.2 Redraft Site Plan and update site (using existing plan) Paul 09 March 2017 13 March 2017 5 100% 3
4.3 Circulate draft site plan with comms plans Paul 13 March 2017 14 March 2017 2 100% 2
4.4 Comments on site plan back to project coordinator Ruchir/Comms/PT 19 March 2017 19 March 2017 1 100% 0
4.5 Revise & Circulate draft site plan for sign off Paul 19 March 2017 20 March 2017 2 100% 1
4.6 Meeting with Learning and Sustainability Scotland Paul 19 March 2017 19 March 2017 1 100% 0
4.7 Global Goals initial site plan signed off (Ruchir) Ruchir 21 March 2017 23 March 2017 3 100% 3
5 GlobalGoals Website Construction Paul 20 March 2017 02 May 2017 44 100% 32
5.1 Meeting with Calum to run through brief Paul/Calum 20 March 2017 20 March 2017 1 100% 1
5.2 Site adapted to fit new brief Calum 20 March 2017 26 March 2017 7 100% 5
5.3 Site reviewed by Project Team and comments back to Calum Project Team 27 March 2017 28 March 2017 2 100% 2
5.4 First meeting of SDG working group (will determine progress and new timelines) Paul, Ruchir 28 March 2017 28 March 2017 1 100% 1
5.5 SDG working group to feedback SDG worknig group 29 March 2017 31 March 2017 3 100% 3
5.5 Revisions to brief based on working group feedback Paul 03 April 2017 09 April 2017 7 100% 5
5.6 Any changes made to site Calum 10 April 2017 16 April 2017 7 100% 5
5.7 Content for Global Goals site - SDGs mapping Scottish Context etc. Paul 17 April 2017 23 April 2017 7 100% 5
5.8 Any changes made to site Calum 24 April 2017 30 April 2017 7 100% 5
5.9 Stage 1 site signed off (Ruchir) Ruchir 01 May 2017 02 May 2017 2 100% 2
6 Sustainable Development Goals Network Paul 01 March 2017 26 May 2017 87 72% 63
6.1 Initial meetings to scope progress and next steps with SDG movement in Scotland Paul 01 March 2017 30 March 2017 30 100% 22
6.2 Planning framework of network and seeking feedback Paul 31 March 2017 06 April 2017 7 100% 5
6.3 Feedback from stakeholders Paul 07 April 2017 01 May 2017 25 100% 17
6.4 Terms of reference for network and meetings set up Paul 01 May 2017 14 May 2017 14 0% 10
6.5 Review of progress Paul 17 May 2017 26 May 2017 10 0% 8
7 Open Government Network Paul 20 March 2017 12 June 2017 85 43% 61
7.1 Initial meetings to scope progress and next steps with OG movement in Scotland Paul 20 March 2017 18 April 2017 30 100% 22
7.2 Planning framework of network and seeking feedback Paul 18 April 2017 24 April 2017 7 100% 5
7.3 Feedback from stakeholders Paul 24 April 2017 18 May 2017 25 0% 19
7.4 Approach and terms of reference for network and meetings set up Paul 18 May 2017 31 May 2017 14 0% 10
7.5 Review of progress Paul 03 June 2017 12 June 2017 10 0% 6
8 Equalities Event One (CEMVO) Allan 12 April 2017 28 May 2017 47 76% 33
8.1 Meeting with partners Paul/Allan 12 April 2017 18 April 2017 7 100% 5
8.2 Event planning Paul/Allan 18 April 2017 17 May 2017 30 100% 22
8.3 Event Paul/Allan 17 May 2017 28 May 2017 12 0% 8
9 Equalities Event Two (YOUNG SCOT) Paul/Allan 01 May 2017 18 June 2017 49 14% 35
9.1 Meeting with partners Paul/Allan 01 May 2017 07 May 2017 7 100% 5
9.2 Event planning Paul/Allan 08 May 2017 06 June 2017 30 0% 22
9.3 Event Paul/Allan 07 June 2017 18 June 2017 12 0% 8
10 Equalities Event Three (INCLUSION SCOTLAND) Allan 27 April 2017 01 June 2017 36 18% 26
10.1 Meeting with partners Allan 27 April 2017 03 May 2017 7 100% 5
10.2 Event planning Allan 03 May 2017 01 June 2017 30 0% 22
10.3 Event Allan 26 May 2017 26 May 2017 1 0% 1
11 Evaluation Planning Ruchir 01 May 2017 30 May 2017 30 100% 22
11.1 Finalise approach for evaluation at end of project Ruchir 01 May 2017 30 May 2017 30 100% 22